§ 550.182. When may the Secretary cancel a lease at the exploration stage?
110 words·~1 min read·
/us/cfr/t30/s§ 550.182·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
BOEM may not approve an exploration plan
(EP)under 30 CFR part 550, subpart B, if the Regional Supervisor determines that the proposed activities may cause serious harm or damage to life (including fish and other aquatic life), property, any mineral deposits, the National security or defense, or to the marine, coastal, or human environment, and that the proposed activity cannot be modified to avoid the condition(s). The Secretary may cancel the lease if:
(a)The primary lease term has not expired (or if the lease term has been extended) and exploration has been prohibited for 5 years following the disapproval; or
(b)You request cancellation at an earlier time.
Connections1 off-index
1 reference not yet in our index
- 30 CFR 550
Citation graph
cites case law
§ 550.182
When may the Secretary cancel a lease at the exploration stage?
Cite30 CFR 550
Cites 1Cited by 0 across 0 sources